Replacement of the Bill Walker Pool Demolition began on March First
Construction began on April Ninth Concrete work for locker rooms is complete
Laying of cinder blocks for locker rooms has begun Steel erection should begin 08-23-18
Building is expected to be completely enclosed by Christmas Myrtha can begin work

Projected completion date is mid-June of next year Project is on schedule